IT service levels offered at the summit.
1 Introduction¶
Service levels offered at the summit.
2 Service Levels¶
2.1 Level 0¶
Verification of fibers state prior to the startup process.
Summit: | 1 FTE |
---|---|
Base: | 0 FTE |
Time: | 3 hours |
Activity | Location | IPAM Link |
---|---|---|
Visual inspection | N/A | N/A |
Fiber checks | N/A | N/A |
2.2 Level 1¶
Minimal connection at the summit with link to the base. Wired and Wireless are available.
Requires verification of the AURA DWDM at Casete Pachion with NOIRLab
Summit: | 2 FTE |
---|---|
Base: | 1 FTE |
Time: | 6 hours |
Device | Location | IPAM Link |
---|---|---|
Core Switches | Rack ? | link |
Distribution Switches | Rack ? | link |
Wireless Lan Controller | Rack ? | link |
Access Switches | Rack ? | link |
DWDM | Rack ? | link |
Core Cluster | Rack ? | link |
DNS | Rack ? | link |
DHCP | Rack ? | link |
2.3 Level 2¶
Level 1 + Telephony and Video Conference.
Requires reset of all IP phones.
Summit: | 1 FTE |
---|---|
Base: | 0 FTE |
Time: | 3 hours |
2.4 Level 3¶
Level 2 + Monitoring
Summit: | 1 FTE |
---|---|
Base: | 0 FTE |
Time: | 6 hours |
Device | Location | IPAM Link |
---|---|---|
APIC 1 | Rack ? | link |
Leaf 01 and 03 | Rack ? | link |
APIC 2 and 3 | Rack ? | link |
Border Leafs | Rack ? | link |
Remaining Leafs | Rack ? | link |
HVAC Server | Rack ? | link |