ITTN-020: Summit Service Levels

  • Cristian Silva

Latest Revision: 2020-06-25

Note

This technote is not yet published.

IT service levels offered at the summit.

1   Introduction

The following is the list of the different service levels that IT can provide at the Summit.

Each service level details the resource requirements and the expected time required to deliver the service. The time includes the startup and verification of IT, but it does not include the verification of the service by the end user.

2   Service Levels

2.1   Level 0

Verification of fibers state prior to the startup process.

Summit:1 FTE
Base:0 FTE
Time:3 hours
Activity Location IPAM Link
Visual inspection N/A N/A
Fiber checks N/A N/A

2.2   Level 1

Minimal connection at the summit with link to the base. Wired and Wireless are available.

Requires verification of the AURA DWDM at Caseta Pachon with NOIRLab

Summit:2 FTE
Base:1 FTE
Time:6 hours
Device Location IPAM Link
Core Switches Rack ? link
Distribution Switches Rack ? link
Wireless Lan Controller Rack ? link
Access Switches Rack ? link
DWDM Rack ? link
Core Cluster Rack ? link
DNS Rack ? link
DHCP Rack ? link

2.3   Level 2

Level 1 + Monitoring and building cameras

Summit:1 FTE
Base:0 FTE
Time:6 hours
Device Location IPAM Link
APIC 1 Rack ? link
Spine 1 then Spine 2 Rack ? link
Leaf 01 and 03 Rack ? link
APIC 2 and 3 Rack ? link
Border Leafs Rack ? link
Remaining Leafs Rack ? link
HVAC Server Rack ? link
3rd Floor Switch Camera Rack ? link
5th Floor Switch Camera Rack ? link

2.4   Level 3

Level 2 + Main Computing

Requires 1 extra FTE from Software group to verify the software.

Summit:1 FTE
Base:1 FTE
Time:4 hours
Device Location IPAM Link
Amor cluster Rack link
Andes cluster Rack link
Azar cluster Rack link

2.5   Level 4

Level 3 + calibration hill

Summit:2 FTE
Base:1 FTE
Time:3 hours
Device Location IPAM Link
Weather, Dimm and All-Sky Cab.
Main Generator Cabinet

2.6   Level 5

Level 4 + Building

Requires reset of ip phones.

Summit:2 FTE
Base:1 FTE
Time:6+ hours
Device Location IPAM Link
1st Floor (incl. GeoVictoria)
3rd Floor (incl. M2, Hex-Rot,etc)
5th Floor
Upper Levels Wifi

2.7   Level 6

Level 5 + Auxtel

Requires reset of ip phones in Auxtel.

Summit:2 FTE
Base:1 FTE
Time:2 hours
Device Location IPAM Link
Auxtel Rack

2.8   Level 7

Level 6 + Telephony and Video Conference.

Requires reset of all IP phones.

Summit:1 FTE
Base:0 FTE
Time:3 hours
Device Location IPAM Link
Cisco BE6K Rack link
Video Conference Conf. Room

2.9   Level 8

Level 7 + all the rest

Summit:2 FTE
Base:0 FTE
Time:4 hours
Device Location IPAM Link
Summit Villa
Contractors Network
Casino
Any other